MOC
Routing Tool

Classify your proposed change, screen it against OSHA PSM 1910.119(l) triggers, determine the required review pathway, and generate a pre-populated MOC checklist. For PSM-covered facilities using any change management program.

OSHA 1910.119(l)4 MOC Classifications Risk ScreenerReview Pathway MOC ChecklistPrint-Ready
📝
Change Description
Describe the proposed change
🏷️
Step 1 — Is This a "Replacement in Kind"?
If yes, no MOC is required by OSHA 1910.119(l)

A Replacement in Kind (RIK) is a change that meets the original design specification exactly — same equipment, same material, same procedure. If any specification differs, it is a change requiring MOC.

?
Does this change meet the original design specification in every respect — same equipment type, same materials of construction, same P&ID configuration, same operating limits?
📂
Step 2 — Change Category
What type of change is being made?
⚠️
Step 3 — Risk Screener
Answer each question — a "Yes" escalates the review pathway
MOC Classification & Routing
📋
AWAITING INPUT
Complete the screener to classify this change

Need a Custom MOC Workflow?

This tool routes standard changes. PSM-covered facilities often need custom MOC workflows integrated with their permit system, PHA re-validation triggers, training records, and document control. SafeGuard Projects builds digital MOC systems tailored to your site's program.

Discuss a Custom MOC System →
📚 MOC Reference — OSHA 1910.119(l) Requirements ▸ Expand
OSHA 1910.119(l) MOC Requirements
RequirementDetails
Technical basisDocument the technical rationale for the change
Impact on safetyAssess impact on safety and health
Modifications to proceduresUpdate all affected SOPs before startup
Necessary time periodDefine duration — especially for temporary changes
AuthorizationRequire sign-off per site's authorization matrix
Employee notificationNotify and train all affected employees before startup
Process hazard analysisMay trigger PHA re-validation if significant change
MOC Classification Summary
ClassTriggerTypical Timeline
RIKExact replacement — no spec changeNo MOC needed
StandardMinor change, low risk, no PSM triggers1–5 days
MajorSignificant change, PHA or SIS impact5–30 days
EmergencySafety-critical, requires expedited review24–72 hrs